A
aydmartin
I am going to fit a 3 phase 6kw immersion heater in a 500litre cylinder. this forms part of a 30kw GSHP system. The immersion is required as top up when the GSHP is not enough to generate enough hot water and the immersion kicks in via GSHP control to lift the temp further. It is also required as a stand alone back up system for when the GSHP is under maintanence or out of order.
I was contemplating running a supply from the C/U to the immersion and separate supply direct from the GSHP resulting in one load but 2 supplies.
Does anyone have any ideas as best way to do this. I believe there are isolators available to utilise this but i have never seen let alone used?
Or is a relay system the best way?
Any advice would be helpfu
I was contemplating running a supply from the C/U to the immersion and separate supply direct from the GSHP resulting in one load but 2 supplies.
Does anyone have any ideas as best way to do this. I believe there are isolators available to utilise this but i have never seen let alone used?
Or is a relay system the best way?
Any advice would be helpfu