Did a mock exam today and not too happy with answer to a question, well 2 actually. Ill give the questions and would appreciate people's ideas to answers as the lecturer didn't seem clear, infect he changed one of his answers to match my answer!
First one:
Which of the following earthing system would you expect to find connected to a caravan pitch
A: tncs
B: tt
C: tnc
D: tns
Second question:
Diagram showing a dp switch marked on/off supplying an immersion heater, question is - the intended purpose of the dp switch with on and off positions clearly marked is to provide
A: emergency switching
B: switching by skilled persons only
C: isolation and protection
D switching off for mechanical maintenance
What would your answers be?
First one:
Which of the following earthing system would you expect to find connected to a caravan pitch
A: tncs
B: tt
C: tnc
D: tns
Second question:
Diagram showing a dp switch marked on/off supplying an immersion heater, question is - the intended purpose of the dp switch with on and off positions clearly marked is to provide
A: emergency switching
B: switching by skilled persons only
C: isolation and protection
D switching off for mechanical maintenance
What would your answers be?