This is the model of contractor causing me problems
Has anyone had any experience with these schneider dol stop start contractors before.?
Basically I'm trying to supply a three phase motor via a timeclock
This works no problem switching the coil of the contractor however the
start button does not hold the coil in to override the timeclock, you have to manually hold
the button on, also the stop button does not break the coil when the timeclock is running.
It's should be straight forward to do this but I seem to be going round in circles!
More experienced in single phase contractors than these!
Any help or advice would be brilliant
This is the model of contractor causing me problems
Has anyone had any experience with these schneider dol stop start contractors before.?
Basically I'm trying to supply a three phase motor via a timeclock
This works no problem switching the coil of the contractor however the
start button does not hold the coil in to override the timeclock, you have to manually hold
the button on, also the stop button does not break the coil when the timeclock is running.
It's should be straight forward to do this but I seem to be going round in circles!
More experienced in single phase contractors than these!
Any help or advice would be brilliant