Hi all .First post .
I'm an electrician working for a solar company company.
We have a commercial solar install starting tomorrow.
The array is split into three lots of 33kw . I can't be certain on very more details than that for the time being.
It will have 3 single phase inverters but be fed via a three phase supply. My boss wants to meter it at the switch room db. (origin of supply) . Then split the phases at the location of the inverters via a connection box and not use a DB.
Is it me or is he out of his tree ? I full intend to force him to consult the niceic over this. But I would very much like to confidently tell him that he is a numpty when I see him in the morning .
Shirley he either needs to install a DB at the inverter location or run three separate circuits from the origin of supply ?
What do you guys think ?
I'm an electrician working for a solar company company.
We have a commercial solar install starting tomorrow.
The array is split into three lots of 33kw . I can't be certain on very more details than that for the time being.
It will have 3 single phase inverters but be fed via a three phase supply. My boss wants to meter it at the switch room db. (origin of supply) . Then split the phases at the location of the inverters via a connection box and not use a DB.
Is it me or is he out of his tree ? I full intend to force him to consult the niceic over this. But I would very much like to confidently tell him that he is a numpty when I see him in the morning .
Shirley he either needs to install a DB at the inverter location or run three separate circuits from the origin of supply ?
What do you guys think ?