- Reaction score
- 1
Hi! Currently doing a job that they have decided against getting gas meters and going all electric.
Electric boiler 9.5kw
2x shower 9.5kw
Hob say 6.5kw
2x 32a ringmains
2x 6a lighting circuits
I understand they have had a 13Kva supply installed.
Obviously this will not be enough to run all that?
Going forward on this would it be better to ring supplier for an upgrade? (3phase or 100a?)
Or if i loose a shower would this then be ok?
Electric boiler 9.5kw
2x shower 9.5kw
Hob say 6.5kw
2x 32a ringmains
2x 6a lighting circuits
I understand they have had a 13Kva supply installed.
Obviously this will not be enough to run all that?
Going forward on this would it be better to ring supplier for an upgrade? (3phase or 100a?)
Or if i loose a shower would this then be ok?