We've just installed a new 3-phase PV system onto a rebuilt community centre, where the pan is to bring in a new 3-phase supply. The new supply has been delayed, and the clients want to get the building up and running.

We can easily use a single phase conversion kit in the DB to provide power to all other services, but they have stated the Building Control officer won't sign of the building until the PV has been commissioned!

We have a three phase SMA inverter and 1 single string of panels, meaning that it's nigh on impossible to amend the wiring and opt for single phase inverters at this stage.

Am I right in thinking that there's literally nothing we can do to get the system commissioned and MCS certification generated?

Thanks in advance
 
Does the design need the PV to meet Part L? How many kWp and what make/model are the panels?

Yes, our PV and an air source heat pump were both a big part of the planning process, and are required (just a shame the main contractor didn't think that he'd have to give WPD lots of notice to bring the new supply in!)

We have an SMA STP5000TL-20 inverter powering 1 single string of 18No LG300w B3 Neons. The route from the inverter/mains position up onto the roof is virtually inaccessible now - I did look into the feasibility of installing 3 single phase inverters as an option before posting.
 
If time critical then, temporarily fit the smallest single phase inverter that will take that number of panels, commission, then swap inverter later.
 
If time critical then, temporarily fit the smallest single phase inverter that will take that number of panels, commission, then swap inverter later.

That's just it, I'm struggling to find a single phase inverter that'll handle that loading (5.49kWp). Any assistance would be appreciated.
 
I thiink a few will take the power (SMA & ABB) but not the voltage as a single string. Perhaps run some temp cables from the roof externally to split string into two?
 
I thiink a few will take the power (SMA & ABB) but not the voltage as a single string. Perhaps run some temp cables from the roof externally to split string into two?

That was my findings too. The idea of having to re-attend and get additional cables onto the roof at this stage, with no access equipment on site, is bringing me to tears.... and all this just as a temporary measure! We'd then have to return again and re-instate the 3-phase setup. Madness
 
Looks like both those suggestions would work. The theoretical maximum power is a bit high but that will not be an issue until the spring by which time you can have swapped to 3 phase.
 

Reply to Building Control Issue in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

Similar Threads

We are refurbishing an empty commercial building at the minute and I don't do commercial stuff day in day out so not entirely clued up on...
Replies
11
Views
1K
Hello, Looking for some advice following a botched 3 phase upgrade today. Some background: Commercial unit originally fitted out (4 years ago)...
Replies
7
Views
501
I (well, the MCS installer) obtained approval under G59 back in 2015 for 11.5 kW of grid connection on a single phase. 12kW of panels into two 6kW...
Replies
3
Views
1K
hi guys i'm trying to get my head round the following setup growatt TL3 5kW 3 phase string inverter 14 panels @ 395W Spa3000 TL ac coupled...
Replies
1
Views
701
Hi all, total newbie to the forum. I sincerely hope that those in the know-how would be able to assist me. On my semi-detached house we have an...
Replies
13
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock