C

Clayden

Im abit confused. Hope some1 can help.
We've just finished wiring 8 small office units. Each one has a sub-mains, fed with a 3c 16mm swa cable. All are ran back to a central point in the metre building. I am going to run all the SWA's on cable tray into a 3 phase consumer unit with seperate isolators for the buildings and 25mm tails out of the consumer unit. The builder has spoken to central networks and have sent him a checklist for us to complete before they can come and connect. They are bringng a new 3phase feed into the meter cuboard. I am unsure what some of the terms mean on the checklist due to me having a mainly domestic background and have never needed to have much cominication with centre networks. If someone could explain to me what i need to supply them with itd be greatly apreciated. Especially involving the CT chamber. This is the checklist:-

Have you:
1- Installed the CT chamber? (only applicable in MPAN 12 area)
2- Installed the main switch or isolator to BS 7671?
3- Provided metre tails and lugs as per instruction from the DNO?
4- Provided with a completion certificate

Thankyou.
 
Im abit confused. Hope some1 can help.
We've just finished wiring 8 small office units. Each one has a sub-mains, fed with a 3c 16mm swa cable. All are ran back to a central point in the metre building. I am going to run all the SWA's on cable tray into a 3 phase consumer unit with seperate isolators for the buildings and 25mm tails out of the consumer unit. The builder has spoken to central networks and have sent him a checklist for us to complete before they can come and connect. They are bringng a new 3phase feed into the meter cuboard. I am unsure what some of the terms mean on the checklist due to me having a mainly domestic background and have never needed to have much cominication with centre networks. If someone could explain to me what i need to supply them with itd be greatly apreciated. Especially involving the CT chamber. This is the checklist:-

Have you:
1- Installed the CT chamber? (only applicable in MPAN 12 area)
2- Installed the main switch or isolator to BS 7671?
3- Provided metre tails and lugs as per instruction from the DNO?
4- Provided with a completion certificate

Thankyou.

2,3 and 4 are routine requirements, the terminology is a bit dated, 4 being an Electrical Installation Certificate.

I've never been asked to provide a CT chamber, this has traditionally always been done by the DNO (Bemco unit or equivalent).

Maybe the builder needs to check the terms agreed to on the initial application for supply.
 

Reply to Central network checklist. in the Industrial Electrician Talk area at ElectriciansForums.net

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock