hello
i have been asked to install a kiosk at a farm entrance to accept 100 a 3 phase,RURAL TT ,at present there is a bungalow slap in the middle of the farm which is being supplied direct from dno very badly i may add with numerous pvc tape over the cable joints in the trees it is 2 core cable around 50 yrs old 240 1 phase.
we wish to have the 3 phase into new kiosk,supply to farm 25mm/plus also a new cable to dwelling 10mm
both underground/both protected with farm 100ma 100 rcd/house 63 amp 100ma s type delayed,both in the kiosk with 100 amp isolator.
delemma ,the bungalow will become offices once the supply is connected to it from the new install.
edf energy want a certificate before connection,but i have no idea of fuse at supply/no ze to start with and earth reading was going to be assessed on install day and measured by ELI-TESTER
WHAT CERT DO THE DNO WANT NEW/ALTERATION/OR MINOR WORKS,also we can only get supply of 63amps onto farm max 3 phase.
how can you issue cert as only have insulation/polarity/r1+r2, do i only fill in what is done at present time,i am only doing this install as the main electrician is stuck abroard in his holiday home and will be for some time,so i am retired 2 years and have been asked to assist with this,after 40 years as installer or heavy duty motor control and motors i am out of the loop a littlebit,also i am not touching the dwelling apart from reconnecting a temporary supply with new 63amp switchfuse/new meter,new tails and new earth rod at house the house set up is a RCD 30ma mcbs .
any thoughts please as it can all be certified in near future when main electrician gets back june/july
construction starts in may on buildings.
 
WPD have never asked for a cirtificate to put a new supply to kiosk. They simple come out tell us where to put the duct to so they can joint onto the cable and that about it, new service in kiosk and wait for the meter to be fitted.
 
hello
i have been asked to install a kiosk at a farm entrance to accept 100 a 3 phase,RURAL TT ,at present there is a bungalow slap in the middle of the farm which is being supplied direct from dno very badly i may add with numerous pvc tape over the cable joints in the trees it is 2 core cable around 50 yrs old 240 1 phase.
we wish to have the 3 phase into new kiosk,supply to farm 25mm/plus also a new cable to dwelling 10mm
both underground/both protected with farm 100ma 100 rcd/house 63 amp 100ma s type delayed,both in the kiosk with 100 amp isolator.
delemma ,the bungalow will become offices once the supply is connected to it from the new install.
edf energy want a certificate before connection,but i have no idea of fuse at supply/no ze to start with and earth reading was going to be assessed on install day and measured by ELI-TESTER
WHAT CERT DO THE DNO WANT NEW/ALTERATION/OR MINOR WORKS,also we can only get supply of 63amps onto farm max 3 phase.
how can you issue cert as only have insulation/polarity/r1+r2, do i only fill in what is done at present time,i am only doing this install as the main electrician is stuck abroard in his holiday home and will be for some time,so i am retired 2 years and have been asked to assist with this,after 40 years as installer or heavy duty motor control and motors i am out of the loop a littlebit,also i am not touching the dwelling apart from reconnecting a temporary supply with new 63amp switchfuse/new meter,new tails and new earth rod at house the house set up is a RCD 30ma mcbs .
any thoughts please as it can all be certified in near future when main electrician gets back june/july
construction starts in may on buildings.
New installation = EIC Electrical Installation Certificate. But your Electrician should know what certificate to supply
 
Dead testing only to show the installation is safe to be connected and energised.
 

Reply to certificate in the UK Electrical Forum area at ElectriciansForums.net

Similar Threads

Background: I am not an electrician, I am a retired professional engineer high power broadcast transmitter design , but am dabbling outside my...
Replies
15
Views
2K
Hello Need to replace a distribution board in the next few weeks to allow for more circuits to be installed in January. Existing is a TT system...
Replies
6
Views
1K
I'm in the middle of preparing a quote for installing 12 x 3Kw and 4 x 2Kw halogen heaters in a church. The system design was provided by a...
Replies
27
Views
965
Hi there, I built a house with ground source heating 5 years ago and it's a fairly large house so I have 3 phase supply 80 amps per phase. I had...
Replies
7
Views
903
HI I am not a professional electrician but have cabled all my houses since starting to build them 30 years ago. I know a dangerously small...
Replies
5
Views
599

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Electrical Forum

Welcome to the Electrical Forum at ElectriciansForums.net. The friendliest electrical forum online. General electrical questions and answers can be found in the electrical forum.
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock