So the situation is this:

Historic 4 story townhouse to 4 flats conversion.
Supplier 3-phase cut out coming in at basement level (One of these will have a 60amp fuse, unsure whether the other 2 contain solid links or additional 60amp fuses yet).
1 phase feeding basement.
4-core SWA containing 2 phases + N&E about 10m in length feeding a Ryefield on 1st floor (UKPN describe this as a riser).
Ryefield contains 3 x 60A fuses with 16mm T&E sub mains feeding CUs in flats.

Now my question is:
Do I need a TP&N fused isolator installed just after the cut-out protecting the riser, which in turn feeds the Ryefield? My current thinking is if cut out contains solid links then yes, if it contains 60 fuses then no - otherwise you're going to have 3 x 60 fuses on each conductor within 10m of cable.
 
So the situation is this:

Historic 4 story townhouse to 4 flats conversion.
Supplier 3-phase cut out coming in at basement level (One of these will have a 60amp fuse, unsure whether the other 2 contain solid links or additional 60amp fuses yet).
1 phase feeding basement.
4-core SWA containing 2 phases + N&E about 10m in length feeding a Ryefield on 1st floor (UKPN describe this as a riser).
Ryefield contains 3 x 60A fuses with 16mm T&E sub mains feeding CUs in flats.

Now my question is:
Do I need a TP&N fused isolator installed just after the cut-out protecting the riser, which in turn feeds the Ryefield? My current thinking is if cut out contains solid links then yes, if it contains 60 fuses then no - otherwise you're going to have 3 x 60 fuses on each conductor within 10m of cable.
Why only 2 phases ?
 
Why only 2 phases ?
So the three-phase incoming supply has been split as follows:
Phase 1 > basement flat CU
Phase 2 > 1st-floor Ryefield > ground floor CU + first floor CU
Phase 3 > 1st-floor Ryefield > second floor CU

The SWA needs re-doing and tbh I think I'll spec an additional core to bring all three phases up to the ryefield anyway. Just allows for more options in the future.
 
So the three-phase incoming supply has been split as follows:
Phase 1 > basement flat CU
Phase 2 > 1st-floor Ryefield > ground floor CU + first floor CU
Phase 3 > 1st-floor Ryefield > second floor CU

The SWA needs re-doing and tbh I think I'll spec an additional core to bring all three phases up to the ryefield anyway. Just allows for more options in the future.
Are you not using the sheath bas the Earth then?
 
Sorry if people are struggling to follow me on this one.

In short, normally you'd want to have a fused isolator on a sub main. Do you however need to do this for a 'riser', given its not DNO property but sits after their cutout fuses and before the Ryefield, again with its own main fuses?
 
Sorry if people are struggling to follow me on this one.

In short, normally you'd want to have a fused isolator on a sub main. Do you however need to do this for a 'riser', given its not DNO property but sits after their cutout fuses and before the Ryefield, again with its own main fuses?

Sorry if people are struggling to follow me on this one.

In short, normally you'd want to have a fused isolator on a sub main. Do you however need to do this for a 'riser', given its not DNO property but sits after their cutout fuses and before the Ryefield, again with its own main fuses?

Bit risky is that
2 phases to a three phase board you might want to consider your options Mate.
 

Reply to Do I need a TP&N fused isolator? in the UK Electrical Forum area at ElectriciansForums.net

Similar Threads

Can someone sanity check my thinking please.... An 80 amp PME service head, tails to meter, 25 sq mm tails into an enclosed fused isolator with...
Replies
4
Views
1K
About 15 years ago, after having had a modern consumer unit fitted, and prompted by our electrician, I asked my then energy supplier (Tonik) if...
Replies
25
Views
5K
I don't "do" solar, but I've been asked to comment on an aspect of a new domestic solar installation by others. There is no overload or fault...
Replies
7
Views
1K
Looking for some guidance here. I'm currently shadowing a guy and we're testing a new extension on a school. 3 phase TNCS supply from the original...
Replies
6
Views
2K
Morning all, I’m scratching my head with this and granted I don’t do a lot of commercial work. Hence I thought I’d ask. Setup is a pub with a...
Replies
12
Views
2K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Electrical Forum

Welcome to the Electrical Forum at ElectriciansForums.net. The friendliest electrical forum online. General electrical questions and answers can be found in the electrical forum.
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock