On an installation there are two main switch’s one in a 12 way DB, another is an exel switch fuse supplying two DB’s. What would you put down as the main switch on the cert on page 2?
Thanks
 
Instyle LED Lighting Specialists UK
This official sponsor may provide discounts for members

telectrix

-
Mentor
Arms
Esteemed
i'd be doing a schedule of test results for each DB. then on each put the main switch details for each. on the inspection section, note saying "see DB schedules"
 
It's asking for the main switch, there is no main switch. What would seeing the schedules prove.
 

telectrix

-
Mentor
Arms
Esteemed
my bad. was looking at an old schedule where each had a main switch details for the DB.
 

TJ Anderson

-
Mentor
Arms
Esteemed
If it has no isolator from DNO and the origin of supply is split then the most comprehensive way would be to complete 2 seperate certs.

It's no different to having a unrestricted and off peak supply at a house, some people do it on two certs and others just add a schedule of inspections and a schedule of tests, not right really but not a big deal in my eyes.
 