Hi Guys

Thinking of opening up a Stand n Tan shop just outside newcastle(NE). Been and looked at the premises and its got a 40A meter installed. How much to get this changed to a bigger meter and which channels do I go through for it.

Thanks, Mark
 
Bulk Workwear - Clothing Suppliers for the Whole Forum Network
This official sponsor may provide discounts for members
C

Cirrus

  • Thread Starter Thread Starter
  • #2
contact your energy provider as they will be the ones able to look at uprating the main cut-out and prices will vary from supplier to supplier
 
M

mgibson212

  • Thread Starter Thread Starter
  • #3
I have not took the shop yet and do not know who supplies the electric for the premises was just wanting a idea of around how much.
 
C

Cirrus

  • Thread Starter Thread Starter
  • #4
Couldn't tell you. I guess it depends on the incoming supply and how big the incoming cables are as to what size main fuse they can provide.
 
M

mgibson212

  • Thread Starter Thread Starter
  • #5
ok, thanks. have contacted NEDL to start things off and will see what comes of it.
 
C

Cirrus

  • Thread Starter Thread Starter
  • #6
Let us know how you get on - will be interested to know.;)
 
P

PAUL M

  • Thread Starter Thread Starter
  • #7
Correct Me If Im Wrong Cirrus But Dont Most Sunbed Shops Need A 3 Phase Supply,just A Thought.
 
M

mgibson212

  • Thread Starter Thread Starter
  • #8
Can get sunbeds in both single phase and 3 phase. Single phase you are looking at around 48 tubes at 160W each which will then need a 8KW spur from DB. This gives around 35A on start up. Limits me to one unit at moment

Tube options Capacity(watts) Fuses single phase three phase
44 x 160W
7340 45A 3x16A
48 x 160W
7980 45A 3x16A
60 x 160W
9900 63A 3x25A
44 x 180W
8220 45A 3x16A
48 x 180W
8940 45A 3x16A
60 x 180W
11100 63A 3x25A
44 x 200W
9100 63A 3x25A
48 x 200W
9900 63A 3x25A
48 x 225W
11100 63A 3x25A
60 x 200W 12300 63A 3x25A
60 x 225W
13800 63A 3x25A
Electrical supply on all units: 230/400V-50Hz


Hope this gives you some more info if interested
 
Last edited by a moderator:
Instyle LED Lighting Specialists UK
This official sponsor may provide discounts for members

Reply to Electric meter change in the Industrial Electrician Talk area at ElectriciansForums.net

uHeat Banner - Forum Discount Available
This official sponsor may provide discounts for members
Top Bottom