Leesparkykent
Esteemed
- Reaction score
- 9,113
I'm looking at a job at the mo where its looking like there is going to be backup/standby generator. Just wondering if anyone has done a similar install and been involved with the paperwork side of things? As its bigger than 16A per phase would a G59 relay have to be installed, application to UKPN, G59 witness testing etc? or am I barking up the wrong tree. Cheers Lee