Discuss Industrial unit-2 incoming supplies both TNCS in the Commercial Electrical Advice area at ElectriciansForums.net

LewisS

-
Reaction score
12
Hi

Just in the process of completing some remedial works on an industrial unit with two tncs supplies, one is 100a the other 200a and on opposite sides of the building! The main issue picked up from the testing was the lack of bonding to all the site services. This is where im after some help, not a problem to bond incoming gas water building fabric air lines etc but will this need to be linked to the 100a main earthing terminal? I was planning to run my bonding from a new met at the 200a supply as this is bigger and should more then protect the smaller supply.

Any help would be appreciated.

Lewis
 
Not to sure but im hoping they are. Will have a proper look into it tomorrow when back on site. Would the supplier be able to tell me if they are?

Thanks

Lewis
 
Same building i would assume its same source although having said that are you using both supplies?

If not just Met for the 200amp..

Does the site need both supplies?... a standing charge will be x2 to start with but as goes equip' bonding i assume the building was segregated at some point as 2 separate buildings?

If it was was the gas/water etc common supply or independently fed ?

Need more info'
 
Further to what's already been suggested and after ascertaining if the two supplies come from the same DNO source....

You don't say if these two supplies are 3 phase or not?? If they are both single phase, it'll be a good bet that they are on different phases so test just to make sure one way or the other!!
Earthing wise make the 200A supply you're MET and link the other supply (EMT) to that MET and connect all the main bonding cables to the MET. If the building is a steel framed structure, don't forget to bond the steelwork to the MET.
 
Excellent thats the way I had planned on doing it. Both supplies are 3 phase and both currently being used. Single gas meter and water meter so maybe was one building the whole time.

Thanks for your replys
 
Excellent thats the way I had planned on doing it. Both supplies are 3 phase and both currently being used. Single gas meter and water meter so maybe was one building the whole time.

Thanks for your replys


That's all fine, but make ''SURE'' first, that these two supplies do indeed originate from the same DNO source, or you may be in trouble with the set-up described above...
 
Just to follow on from E54. The reason for ensuring the supplies are from the same source is the possibility of circulating currents in any bonding including the building steel work.
Is there any defined areas for the two independent supplies or are they overlapping? It’s not a great problem so long as the origin is known. A simple way is label all sub-boards Supply “A” or “B”.

I’ve had some experience of overlapped supplies renovating a plant switch room. One 433V 600A supply from one substation, four 550V 400A supplies from two other subs. To add to the fun all the 550V supplies could be paralleled. When I started the project I was stood in the middle shaking my head trying to make sense of it all, it's also why I became an AP. It took me near three years on and off to sort out. We ended up with one common MET for all supplies. But this was a private network where everything was cross bonded as a matter of course.
 

Reply to Industrial unit-2 incoming supplies both TNCS in the Commercial Electrical Advice area at ElectriciansForums.net

Similar Threads

Incoming supply on our job comes into the building and then the tails from which go into a switched isolator with 200A fuses fitted. No idea...
Replies
5
Views
942
We are refurbishing an empty commercial building at the minute and I don't do commercial stuff day in day out so not entirely clued up on...
Replies
11
Views
1K
Hello, I have a EV charger that is reporting over voltage and is unable to charge. the charger will operate up to 253V The solar inverter reports...
Replies
6
Views
3K
This is a question (or discussion probably) regarding selecting the main earthing conductor, and subsequently the main equipotential bonding...
Replies
26
Views
6K
Those week I have mostly been fitting 20 x 10W flood lights on the sloping edge of a converted mill ceiling, nothing is straight, nothing level...
Replies
3
Views
1K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock