i have recently finished a periodic test of a fairly large castle and found that the building had no main equipotential bonding conductors. There is around 22 individual consumer units situated around the building all coming via sub main supplies from the main incoming area. Must the main bonding conductors come from the point of incoming supply or can they come from any of the individual consumer units?
 
B

BillR3

  • Thread Starter Thread Starter
  • #2
As long as you have an in spec Zdb at your local consumer units there should be relevant equipotential bonds run from these DB's to associated services/metalwork etc as there should be from the local DB to the point of origin.

Hope this helps

BillR3
 
W

wayne

  • Thread Starter Thread Starter
  • #3
often find two voices singing the same tune helps .as BillR3 said:)
 
Bulk Workwear - Clothing Suppliers for the Whole Forum Network
This official sponsor may provide discounts for members

Reply to main bonding conductors in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net

CK Tools :) The professionals choice when it comes to Electrical Tools
This official sponsor may provide discounts for members
Top Bottom