Interested to know if others take this route?.

If a customer wants a CU Change and have not got any previous electrical records do you PIR first to check the installation and also pick up any remedial.

Then complete the CU Change.

Then supply an EIC.

Comments Appreciated :)

 
thats what i would do, my mate got stung a few years back, got a phone call of a woman he never met went round changed her consumer unit witout testing it first, when he came round to testing the new one sooooo many faults it was untrue.

the woman says well it was allright before!

haha he has never done it again
 
For my own peace of mind, i tend to IR test circuits first and check for borrowed neutrals.

Once thats proved ok, then on with the cu change.
 
I do all the dead testing plus zs to make sure the maximum disconnection times for rcds will be easily met. Of course charge the customer for this 1st test and explain why. It might knock a few customers back from using your services, but it prevents you from potential headaches afterwards.
 
Hi mate
I would generally test before swapping the board and not charge them for the EIC
After fitting £70 pir, charge for remedials £250 board and just issue the EIC

Hope this helps :cool:
 
Hi mate
I would generally test before swapping the board and not charge them for the EIC
After fitting £70 pir, charge for remedials £250 board and just issue the EIC

Hope this helps :cool:


Thanks all for the replies!
 
Last edited by a moderator:
you should always aim to keep cost down for the customer so when you do an estimate check what wiring there is estimate the age look for visual alterations then you should be able to estimate what problems can occur put all this in writing in your estimate and state any fault finding rectification will be carried out on a time and materials basis after all if there are faults they need rectifying so do the change then test then do another estimate for cost of repairs as faults are allways found when testing espicaially with all the new regs .
 

Reply to PIR CU Change and EIC in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock