Hi all,

got an EICR to compile and I'm just wondering whether I should be using L1,2 and 3 on schedule for identifying circuits or just stick with R,Y and B since it has been marked up like that on existing schedules etc?
 
Just thinking it might be a bit confusing with sockets and switches marked up the old way, and schedule marked up the new?
 
i'm with trev on this one. label with both. i call it BS and AS (before stupidity and after stupidity)
 
To be honest, it depends on what's there for me. If its an old DB, then I will keep the RYB designations, but if it's new then I use L1, L2 L3 with the way number in front
 
But by using both you're complying with current regs and making it idiot proof. You could get someone coming in after you at some point who sees the coloured lines and has a head scratch wondering how the colours equate to L1 L2 etc.
 
Well thats why you use the dual wiring colour sticker at the DB.
But you should still be recording 17th edition terminology in the report.
RYB went out in 2006 , time to move on :)
 
In fairness I don't think identification of ways comes under BS 7671 terminology. Certainly for new work I'd be using L1/L2/L3 but as johnboy says I might be reluctant to alter what is already marked up as R/Y/B. It may cause more confusion than it eradicates.
 
Thanks for replies, think the way to go might be to use L1,2,3 on report and mention in "observations" that switches etc have been labelled R,Y,B.
:D
 
I would go with Trev on this one.

You could also put in the recommendations that R = L1, Y = L2 and B = L3 just so the new wave of sparkys don't confuse blue with neutral. As above, idiot proof.
 
Well thats why you use the dual wiring colour sticker at the DB.
But you should still be recording 17th edition terminology in the report.
RYB went out in 2006 , time to move on :)
So what do you do if you're working on one circuit of an existing 18w board ......
R12, Y12, B12.....13L1, 13L2, 13L3.....R14, Y14,B14. Your cert schedule has to match the db, surely. Don't make it more confusing. With Trev, best of both worlds.
 
You should be using L1 L2 L3 for everything, what would you do if your sub-main cable was an old red phase supply that feeds a new coloured DB.
 
So what do you do if you're working on one circuit of an existing 18w board ......
R12, Y12, B12.....13L1, 13L2, 13L3.....R14, Y14,B14. Your cert schedule has to match the db, surely. Don't make it more confusing. With Trev, best of both worlds.

Dont make it more confusing ? its not confusing at all if everyone follows the current guidelines.
 

Reply to R,Y,B or L1,L2,L3 in the Periodic Inspection Reporting & Certification area at ElectriciansForums.net

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock