sdc8843

Hi Guys

I have the possibility of installing up to a 50 KW system on a light industrial unit in East Sussex. The customer is unsure as to the size of system to install but it could probably be up to 50KW.So far only having installed domestic systems up to 16A per phase and am a little bit daunted by the G59 process. I wanted to try and ascertain from UK Power Networks the feasibility of putting this size of system in. When i contacted them i got sent an email with a 9 page form to fill in!


Questions
1. Is there no way of getting a verbal idea of feasibility without submitting this very long winded application form as cost of upgrading may make it a no goer before we start.

2. Any help on deciphering the G59 process would be greatly appreciated.


Many thanks
 

Reply to UK Power Networks in the Solar PV Forum | Solar Panels Forum area at ElectriciansForums.net

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock