P
Phaze-3
Hi guys,
Need to put a 32A 3phase supply in to a 10KVA site transformer using swa. The run is 250m long but would i need to apply 3% or 5% volt drop??
It works out at 3% i need to use a 35mm cable and at 5% i can use 16mm.
Anyone have any idea???
Thanks
Phaze-3
Need to put a 32A 3phase supply in to a 10KVA site transformer using swa. The run is 250m long but would i need to apply 3% or 5% volt drop??
It works out at 3% i need to use a 35mm cable and at 5% i can use 16mm.
Anyone have any idea???
Thanks
Phaze-3