Dear Mr T Wat
Thank you for your letter of xx/xx/xx advising me of the alleged dispute.
It should be noted that it is my intention to issue County Court proceedings within seven days of the date of this letter unless payment of my invoice number xxxxx is received in full before that date. Should this be necessary the full details of the dispute will be required to be made available to me before the date of any court hearing.
You should therefore send me full details of
A) The contractor who carried out the alleged necessary remedial work, including the details of their registraion with a professional body
B) The details of any alleged improper work carried out with full reference to any direct contraventions of BS7671 (2008)(2011)
C) A receipted copy of any invoice raised by this contractor for the alleged remedial work.
D) Copies of all correspondence between us specifically referring to problems with the installation.
I appreciate that at this stage you are not legally obliged to provide the above information however, providing it will speed up any litigation thus providing one of us with a satisfactory conclusion.
I look forward to hearing from you.
Yours sincerely
Dillb.


I'd send em something like that mate, but if you're not confident get a lawyer on the job. Good luck Dillb, ****s like this boil my blood

edit

Or as per post 15, give the massive wedgie. Although opinions of wedgies as a debt recovery tool are somewhat contradictory
 
Last edited by a moderator:
The guys have all given sound advice mate, and I can't really add to what they have said.
Just remember to stand firm. These "mind-game merchants" are very good at making you doubt yourself after a while and you end up thinking "did I actually do something I shouldn't have?".
Hope it gets sorted out soon. Stuff like this just ****es me off.
 
Just done that, but his email too me confirms all I needed too know. Will give him till 1st of September then start proceedings then. Although never seen his payment T&Cs I will give him the benefit of the doubt until then.

I think if you were not made aware of his terms of payment at the outset, then your conditions of sale override his conditions of purchase (terms of payment)

I wouldn't be giving him 14 days to settle with you now .. I'd be issuing a Letter Before Action giving him seven days, then bang it into the court - he'll be liable for the costs & Statutory Interest.

You may also like to have a look at Thomas Higgins (use Google) who are rather good at recovering your money & don't cost you the earth to do it.
 
I think if you were not made aware of his terms of payment at the outset, then your conditions of sale override his conditions of purchase (terms of payment)

I wouldn't be giving him 14 days to settle with you now .. I'd be issuing a Letter Before Action giving him seven days, then bang it into the court - he'll be liable for the costs & Statutory Interest.

You may also like to have a look at Thomas Higgins (use Google) who are rather good at recovering your money & don't cost you the earth to do it.

Have you used this firm GS, and if so, was it a stress-free experience?
 
Dear Mr T Wat
Thank you for your letter of xx/xx/xx advising me of the alleged dispute.
It should be noted that it is my intention to issue County Court proceedings within seven days of the date of this letter unless payment of my invoice number xxxxx is received in full before that date. Should this be necessary the full details of the dispute will be required to be made available to me before the date of any court hearing.
You should therefore send me full details of
A) The contractor who carried out the alleged necessary remedial work, including the details of their registraion with a professional body
B) The details of any alleged improper work carried out with full reference to any direct contraventions of BS7671 (2008)(2011)
C) A receipted copy of any invoice raised by this contractor for the alleged remedial work.
D) Copies of all correspondence between us specifically referring to problems with the installation.
I appreciate that at this stage you are not legally obliged to provide the above information however, providing it will speed up any litigation thus providing one of us with a satisfactory conclusion.
I look forward to hearing from you.
Yours sincerely
Dillb.


I'd send em something like that mate, but if you're not confident get a lawyer on the job. Good luck Dillb, ****s like this boil my blood

edit

Or as per post 15, give the massive wedgie. Although opinions of wedgies as a debt recovery tool are somewhat contradictory
Arrange a meeting with himself and take a witness with you.(record the meeting)
Ask him for a full written report for the other electricians findings explaining what they consider to be wrong and ref' to the regulations that have been breached in their opinion, this will put him on a back step if hes just made it up, express you denial to him requesting you to sort the issue out on numerous occasions, also express that as he supplied the fitting any additional labour and costs replacing them with be an extra to the original invoiced work.
Ask for copies of invoiced work carried out by others to rectify the problem and also the company details so your lawyer can get in touch with them, if at this point he starts avoiding these requests then this is where your witness comes in use confirming his avoidance to give requested details.
Also explain any materials you have supplied are still your property until the bill is settled and failure to do so would see you getting a court order to recover your property, also reminding him that in doing so it will not be financially beneficial to himself and you are willing to make a loss on this job just to ensure he dosn't drag this out or try get reduction in costs.
The Invoice you supplied is what it is your test cert' expresses it compliance and if he wishes to challenge that with an independant electrical firm then he should issue you with a full inspection report on your work from them as mentioned above and at his own cost, unless in a court he can prove your work isnt to reg's then this is when and only when he can recoup their costs.

I dont want too ask for much information as he is rather thick and won't think too bring much information too court should it get that far, so will just raise these things then where I feel he will have no information too hand .

Write to him and ask that he address the following points;
  • You have no record of him failing to contact you with any problems- ask him to detail how and when he raised these issues
  • As other parties have interfered with your work any guarantee is now void, the invoice still stands

You (as said earlier) need copies of reports made by the other electricians- together with their scheme registration details.

Thank him for acknowleging via email that you have carried out works and the amount disputed. Point out to him that you charges are fair and reasonable and you will give him 7 days to pay.

Tell him that legally he can't withold the full invoice value but should pay what he thinks is due, and dispute the rest. By failing to pay he is in breach of contract - this applies even if there is no written contract.

This way you get more of your money but can still go to court for recovery of materials in lieu of payment

He only ever mentioned the problems to me verbally, never asked me to go and have a look.

I think if you were not made aware of his terms of payment at the outset, then your conditions of sale override his conditions of purchase (terms of payment)

I wouldn't be giving him 14 days to settle with you now .. I'd be issuing a Letter Before Action giving him seven days, then bang it into the court - he'll be liable for the costs & Statutory Interest.

You may also like to have a look at Thomas Higgins (use Google) who are rather good at recovering your money & don't cost you the earth to do it.

He has only just mention his payment T&Cs, he has paid pretty quickly before so never had reason too think he would pay 30 days from month end.
 
Have you used this firm GS, and if so, was it a stress-free experience?
I have used them and I would say it was a stress free experience (from the TH end if not from the debtor). LBA letters are easy and did get a response. Haven't gone to court yet but they now will provide help against a defended action whereas before it was only if there was an uncontested debt.
They provide lots of information and help and the costs are not exorbitant.

I dont want too ask for much information as he is rather thick and won't think too bring much information too court should it get that far, so will just raise these things then where I feel he will have no information too hand .

He only ever mentioned the problems to me verbally, never asked me to go and have a look.

He has only just mention his payment T&Cs, he has paid pretty quickly before so never had reason too think he would pay 30 days from month end.
The fact that he agrees the amount clarifies that the amount is due and leaves him only with the faulty installation defence, for which you need more information, I would have thought it unlikely that a lamp failure could occur after 3 weeks due to a faulty wiring arrangement, it would either be immediate or after years.
If he has mentioned the problems, then what was your response since a likely expectation would be that you might address the problem, what does your customer complaint policy state and did you comply with this.
Sorry to sound negative on this one but it is best to cover all angles. I still agree with the others he is a chancer.
30 days EOM is standard but really must be advised beforehand and if you have provided your terms and conditions then they will take precedence.

Just my thoughts, not a legal statement!! Good Luck.
 
My payment terms and conditions are usually upon completion of the job. Having just looked i never stated when payment was due. But now he has emailed me stating he is not paying me surely invalidates any that he may have anyway?

He asked why some lights were not working, I stated that they were working fine when I left the job. It could be faulty lamps or ballasts, nothing. I also stated without actually seeing the job I would be unable to diagnose the fault.

Will type a letter and get that posted today asking for clarification of the faults etc. I am away for 2 weeks from Monday though working so will be a little slow on the response to it.
 
Dilb.... I'm in same situation. 2.5k

Using the fact some coax and 12v cables behind the DVR on a CCTV job are messy.

Took the guy nearly 7 months to bring this to my attention and it was only after I sent final demand!!!

Amazing really! Obviously does not want to pay either!!
 
Have you used this firm GS, and if so, was it a stress-free experience?

Yes I have & yes it was very easy & straight forward & not too expensive.

Back then (1990 ish) everything was done by fax - I sent details of the debtor to Higgins via fax & they issued the necessary paperwork to the debtor.

Most of the time though, I did debt collection myself & was quite successful. In one 12 year period I lost just under £2k which I think isn't too bad overall.

The comment I made above about the Conditions of Sale overriding the Conditions of Purchase is based on what happened to me, and if anyone's interested here's the story: I received a telephone call from a very big company who are best known for making tyres. During the call, I was asked if I could make & supply this company with an item by the end of the week, and I said I could. I was then given an official order number over the phone & told that the order would be posted to me.

I made the item & the customer collected it on the agreed date & signed for it. I then posted the invoice with my payment terms printed on it to them.

Next day, their official order arrived in the post & after I satisfied myself that the number tallied with what I had been given over the phone, I filed it away.

The day that the payment was due came & went without any sign of payment being made, so I posted a reminder & waited a bit longer.

When there was still no sign of payment I issued a Letter Before Action giving 7 days in which to pay. This resulted in my receiving a phone call from someone quite high up in the company asking what the hell I thought I was doing.

I politely explained that as they hadn't paid me I was informing them that I was taking them to court for non-payment of the debt. I was then asked if I had their official order & at that point I pulled it out of the file. I was asked if I had read their Conditions of Purchase which was all the (very) small print on the back. I then read it & found that they were looking for 90 DAYS in which to pay !!

At that point, I said that I had been unaware of this as the whole process had been carried-out over the phone and as I had been unaware of their Conditions of Purchase my Conditions of Sale would take precedence and that meant payment within 30 days of invoice.

I was then asked "Where do we go from here?" to which I replied "You send me a cheque today & I don't take you to court". The cheque arrived the following day.

It was almost a year later when the phone rang & it was the same company asking if they could have another item the same as previous and if so would it be the same price. I told them it would be the same price if they paid Cash on Collection, but if they wanted their Conditions of Purchase to apply it would be 25% more.

They gave me the order number over the phone & paid Cash on Collection.
 
My payment terms and conditions are usually upon completion of the job. Having just looked i never stated when payment was due. But now he has emailed me stating he is not paying me surely invalidates any that he may have anyway?

He asked why some lights were not working, I stated that they were working fine when I left the job. It could be faulty lamps or ballasts, nothing. I also stated without actually seeing the job I would be unable to diagnose the fault.

Will type a letter and get that posted today asking for clarification of the faults etc. I am away for 2 weeks from Monday though working so will be a little slow on the response to it.

In that case make it look like you are being more reasonable
Give them 14 days to pay and request that if they are refusing to pay that they state this in writing
I have the odd clinents like this p, but they only get one job done and then get added to the blacklist- I have a blacklist on my phone that has clients I don't want to have again and also sales calls on this list

I also have a mobile that records ALL calls and a system that records incoming calls- and gives a recorded message saying so BEFORE the call is connected to me, this cuts the sales calls by 90%

In your case it may go to court, so you have to look reasonable and fair

The act you are away for 14 days means you can't reply- use this to your advantage and look more reasonable.
Be firm and don't let then think youre worrried.

Don't write emails in anger- do the reply and re-read it 2-3 Times before sending it
 
Have taken a draft of what trev put into a letter and sent that recorded delivery today. Although I did lose my temper with him on the phone, I have since kept my cool. Will await his reply and post back what he has put.
 
I had a landlord that orders work and does't pay

He did this with a builder and me, but I had a paper (email) trail and call recordings which blew his arguments out the water to such an extent he didn't turn up to court
don't get mad get even
 
Last edited:
Right recieved no reply to 2 letters I have sent him. Time to write a final demand letter stating if payment not recieved in 7 days then legal proceedings will taken against him. Or is there anything else I should do before this?
 
They do recommend making the debtor aware of debt counselling agencies so that they can get advice if they are in trouble.
You should have made all attempts to try to resolve the issue before taking it to court (which I think you have done).

Thereafter stick to your guns and do not back down like I did; I am now 5 months in and will be taking legal action next week, been a bit expensive, but as a friend said to me if you let it go then you will become known as a contractor who does not need to be paid!

INDEPENDENT ADVICE ORGANISATIONS

National Debtline Tricorn House, 51-53 Hagley Road, Edgbaston, Birmingham, B16 8TP FREEPHONE 0808 808 4000
National Debtline – Free, Confidential Debt Advice – Call 0808 808 4000

Consumer Credit Counselling Service (CCCS)
FREEPHONE 0800 138 1111 Debt help | Free debt advice for UK debt problems | Free debt management | CCCS

Citizens Advice
Check your local Yellow Pages or Thomson local directory for address and telephone numberswww.citizensadvice.org.uk

Community Legal Advice (formerly Community Legal Services Direct)
0845 345 4345 www.clsdirect.org.uk
 

OFFICIAL SPONSORS

Back
Top