,Hi all,
This is my first post thus up-front apologies for errors or etiquette infringements
Me: Iām retired now, and just a DIYer, always looking to our next project, using local professionals for installation.
Iāve looked through the forum and found similar items but they are not the same hence this post.
The project, we have a solar installation with storage batteries, and IMHO with the increasing possibilities of power cuts, I want to legally and safely use the solar/batteries during any grid outages.
First question; does anyone have user experience/knowledge of the āGEYA W2R 100A ATSā shown in the schematic? Chosen purely due to space limitations.
Second question, āMust this earth be run to and connected to the main consumer unit (DB1), or can it be terminated in the garage at the distribution unit (DB2), far easier cable routeing.
Many thanks in advance for any feedback/help on the above questions, it will help me when explaining to the electrician exactly what I'm after and why.

This is my first post thus up-front apologies for errors or etiquette infringements
Me: Iām retired now, and just a DIYer, always looking to our next project, using local professionals for installation.Iāve looked through the forum and found similar items but they are not the same hence this post.
The project, we have a solar installation with storage batteries, and IMHO with the increasing possibilities of power cuts, I want to legally and safely use the solar/batteries during any grid outages.
First question; does anyone have user experience/knowledge of the āGEYA W2R 100A ATSā shown in the schematic? Chosen purely due to space limitations.
- Iām considering having one placed between the Smart Meter and Consumer unit, in its own enclosure, and using the Emergency Power Supply output of the grid tied solar inverter as the Back Up supply to the W2R. I have also contacted GEYA and explained the way it is planned to be used including being able to support exported power, and in short, they say its fully compatible and will accept 25mm2 tails.
Second question, āMust this earth be run to and connected to the main consumer unit (DB1), or can it be terminated in the garage at the distribution unit (DB2), far easier cable routeing.
- DB2 is a slave from DB1 and feeds the solar, heat pump and EV charger installations.
Many thanks in advance for any feedback/help on the above questions, it will help me when explaining to the electrician exactly what I'm after and why.




No I meant the reason for setting ATS Enabled not your set up specifcally.