I am half way through a modernisation project and the owners have decided to stay with leccy storage etc, so I am fitting boards to allow for THTC on the last one the "meter guy" came when I was off site and did the poking of cables into the various meter ports, as I had left all tails marked up, anyway I noticed that the iso had no provision the isolate neutral just 4 in 4 out, GLP, Store,Heat & OP Water is this normal, to be honest I have done a few like this and havent given it much thought,