bigbaddave

Completed a rewire back in December, However have had probably 10 calls since due to changes in the original spec.. Now i have been working for a company who is doing the work on behlaf of someone. I have billed for the bulk and been paid however i was going to issue a invoice for the extras (£342 for materials) so no biggy but a couple of days work on top..

Now I was just about to issue a invoice for the work.. However before i do so i get a E-mail through with spec and plans for 7 houses in the same street turns out its on behalf of a council they have just landed contract for a number of there rewires.. Putting materials aside as the money paid on the job more than covers this there is only my time to concider.. Personally im thinking ditching it but the wife rekons im mad.. (See is only peed off as i cancelled a mid week break to go back to the job... But it was only the lakes and well thats another story...
 
If the original changes were discussed and you stated that there would be additional cost, then you should charge for it. If it's one of those "grey areas" which you think may be questioned, and there is more work forthcoming, then maybe accept the big picture. Just don't let them believe they can give you extra work and cost and not have to pay for it. Just my opinion, and hard without being there to get a feel for the situation.
 
"Now I was just about to issue a invoice for the work.. However before i do so i get a E-mail through with spec and plans for 7 houses in the same street turns out its on behalf of a council they have just landed contract for a number of there rewires.."

I would invoice for the works already carried out with the agreement that if you carry out the 7 rewires for the rest of the street, you will knock that amount of money off the end invoice as a show of good relationship.

 