Hi am going to replace a fuse board this week end however had a quick look in the loft space and found there seem to be a hell of a lot of loft installation do I note this on cert due to cables being under it

Cheers

Pete
 
Hi Peter
If in doubt put it down as wont hurt and covers you also are the cables covered for contact with thermal insullation ? just a thought but on cert and pir lable note cu replacement only.
Regards
Kung.
 
Hi am going to replace a fuse board this week end however had a quick look in the loft space and found there seem to be a hell of a lot of loft installation do I note this on cert due to cables being under it

Cheers

Pete

hi pete,your the inspector and wont harm.you could put down a code 3 in the observation and recommendations on certificate.
barry
 
Changing a fuse board - have to do a electrical install cert afterwards.

PIR should state the reasons why fuse board to be changed, and anything else that needs attention. You can't add codes / recommendations on to an elec install cert. Your testing of all circuits afterwards should highlight no concerns. They are issued only when all is well - you are signing it off as a done job !!!!
 
The maximum derating of cables in loft insulation is 50%, so if the load will comfortably never cause the cables to be subjected to that current (or even better, if the MCB is suitably chosen so as to limit the current appropriately), then I don't see the point of noting it on your PIR. Up to you though... As has already been said; if you really want to protect yourself, note it.

Noting it is somewhat academic anyway if you go on to change the board, since then you should either select MCBs to suit the cable installation method(s), or, if you need to drive higher load(s) than the cable/ref method(s) can handle, you'll need to make provision for the cable(s) to take the load, either by seperating them from the insulation, or increasing their csa.
 
You are only changing the CU and the extent of work section on the cert and CU labels should state exactly that.

Dont get carried away with derating the MCB's and cables etc.

You are NOT responsible for it.

Obviously any major problems should be rectified with the most common being main earth & bonding.

Anything else can be noted on the cert in the deviations and comments boxes on the cert.

What do you think happens when a home owner gets a grant to have their loft stuffed with insulation?
 