Hi Guys,

I've just recently qualified and been asked to do a job for a mate. He has half his garage partitioned as a wet room. Contains a shower and extractor fan. His CU is already full and he wants a separate 2 way CU to feed the wet room. Is the best way to go about this to sepeate the tails from the meter into service connector blocks and feed each CU seperately?

Any Suggestions welcome.

Cheers

Andy
 
Hi Andy

Think its best to price the job up on materials only ie is it cheaper to replace consumer unit with a larger one or buy a seperate unit and use a henly block as you suggest then let your mate decide which we he would like it done

Chris

PS dont forget to add your labour charges on afterwards
 
Last edited by a moderator:
Installing a separate CU will be cheaper then changing the CU for a larger, as you will need to do full tests on all the circuits plus the additions.

IF you do decide to install a stand alone CU for the shower etc, then its only that you need certify.

Dont forget to ensure all earthing arrangements are satisfactory.
 
Alternatively, you could put a 50 amp breaker in the original consumer unit to feed a new one, then swap one circuit from the original board into the additional board and hence you have spare ways. This way you only have to test one original circuit and you also only have one main switch, the idea of the company fuse as the sole means of isolation is always an iffy one
 
Alternatively, you could put a 50 amp breaker in the original consumer unit to feed a new one, then swap one circuit from the original board into the additional board and hence you have spare ways. This way you only have to test one original circuit and you also only have one main switch, the idea of the company fuse as the sole means of isolation is always an iffy one


Good solution to the " One Means of Isolation" situation and does away with the henley blocks scenario !........providing the main switch on the existing c.u.is of adequate rating for the additional expected load of course.


spark1;)
 

Reply to Extension to CU in the Australia area at ElectriciansForums.net

Similar Threads

Hi all, Disclaimer: I'm not an electrician and have very basic knowledge of electrical installation. We've been putting in a new kitchen into an...
Replies
17
Views
2K
So a customer had a nuisance trip and I spent 4 hours trying to find the fault (first hour identifying circuits as none labelled at board). There...
Replies
18
Views
2K
I'm converting my old garage into a two bedroom annex. At its nearest point it is approx 10m from main house. I plan it to be all electric, UFH...
Replies
5
Views
3K
Morning All I recently completed my first re wire and board change, (with help from the owner who is a gas fitter and plumper, who works with my...
Replies
0
Views
1K
  • Locked
  • Sticky
Beware a little long. I served an electrical apprenticeship a long time ago, then went back to full time education immediately moving away from...
Replies
55
Views
5K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc
This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock