UK Forum Secondary bonding where the connection to pipework outside the room was via plastic fittings

Dear Folks
I am currently on a job replacing hot and cold water supply pipework under a bath and where originally there were 2 plastic fittings connecting the steel bath and its copper pipework to 'extraneous' pipework in the floor of the bathroom and beyond. Follow link below for image.

Original plastic connectors Note extraneous pipe is coming through the floor not from wall which is actually connects to plastic pipe behind the wall feeding a shower valve

Originally I thought this meant that there was thus not electrical continuity and therefore this bonding would not work. Consequently, I replaced the plastic fittings with copper fittings. Now however I am thinking that I have just possibly introduced an extraneous earth potential and one that may not be properly earthed and therefore will need to be tested. In other words, it was better as it was! All her circuits furthermore have RSBO's.

Completed pipework having removed plastic connectors and redone bonding

Allow me add that I think leaving the old bonding in place was at least confusing for someone like myself less experienced in these matters. Even if I appreciate this was probably done by a DIYer, builder or plumber unmindful of the positive consequences of using plastic fittings to extraneous pipework and consequently less sensitive to the need to also remove secondary bonding in order to underscore the unnecessariness of it.

The first question now however is is the above assessment correct? And if so what should I do now? Am I better, as I think I am, to replace the copper fittings with plastic fittings as was and to remove the secondary bonding possibly writing a note on the underside of the bath pointing out to following-on parties that secondary bonding is thought not necessary as connections to extraneous conductive parts are interrupted by plastic connectors?
 