Remove meter so DNO can replace meter board?

Meter company came to replace meter, but said meter board must be changed by DNO and reported it to them. DNO came, but said we need to remove Schneider cabinet from board, and that meter people must come same time to remove meter and refit after DNO has changed board, and to allow half a day. Well, trying to get DNO and meter company to come samed time as us to work together is a nightmare. Is there any reason why we cannot remove the meter and cabinet while the DNO pulls the fuses, and changes the board, then we can refix to get it up and running and call the meter people when done?
meter board.jpg
 
Last edited:
Meter company came to replace meter, but said meter board must be changed by DNO and reported it to them. DNO came, but said we need to remove Schneider cabinet from board, and that meter people must come same time to remove meter and refit after DNO has changed board, and to allow half a day. Well, trying to get DNO and meter company to come samed time as us to work together is a nightmare. Is there any reason why we cannot remove the meter and cabinet while the DNO pulls the fuses, and changes the board, then we can refix to get it up and running and call the meter people when done? View attachment 125152
Its a pain in the arse isn't it, I wanted an Isolator fitted which should have been straightforward but the cut out was old and contained asbestos so the supplier wouldn't do it had to get the DNO to sort that and then get the supplier to fit the isolator. Actually that wasn't straight forward had to swap supplier because the first supplier wanted proof there was no asbestos when the cut out was a brand new one! They don't seem to talk to each other so I can see your situation being a right pain!

Different DNOs handle this differently as well just to make it worse!

I would try again with the supplier they really should be able to coordinate this with the DNO and obviously yourself with regard to removing the Schneider board.

Worse case if the DNO turn up they should be able to disconnect everything and fit the back board at least. If the supplier fails to show on the agreed time you can escalate to an emergency and they need to be there within 3 hours during the week or 4 hours during the weekend. I would imagine it will be DNO am, supplier pm which equates to the half day without power.

DNO won't refit the meter but should at least disconnect everything and fit the back board. Essentially the same state they would leave it for a new supply ready for the meter to be installed.

Probably wouldn't hurt to do some chasing on the lead up and on the day just to make sure everything is still on track.
 
Its a pain in the arse isn't it, I wanted an Isolator fitted which should have been straightforward but the cut out was old and contained asbestos so the supplier wouldn't do it had to get the DNO to sort that and then get the supplier to fit the isolator. Actually that wasn't straight forward had to swap supplier because the first supplier wanted proof there was no asbestos when the cut out was a brand new one! They don't seem to talk to each other so I can see your situation being a right pain!

Different DNOs handle this differently as well just to make it worse!

I would try again with the supplier they really should be able to coordinate this with the DNO and obviously yourself with regard to removing the Schneider board.

Worse case if the DNO turn up they should be able to disconnect everything and fit the back board at least. If the supplier fails to show on the agreed time you can escalate to an emergency and they need to be there within 3 hours during the week or 4 hours during the weekend. I would imagine it will be DNO am, supplier pm which equates to the half day without power.

DNO won't refit the meter but should at least disconnect everything and fit the back board. Essentially the same state they would leave it for a new supply ready for the meter to be installed.

Probably wouldn't hurt to do some chasing on the lead up and on the day just to make sure everything is still on track.
Thanks for your in-depth assessment. I was thinking of something similar, will have to tell occupier that may be without power most of the day - and if meter people let us down (not unknown, on past experience with them) could even be more than a day. They won't be pleased, but not really in our control. We had a job couple of months ago, DNO and meter people booked in, then DNO rang to say van had broken down. Friday afternoon, (there's a surprise - i wonder??!!) they rang at lunchtime to cancel - took another 5 weeks of phone calls and emails to get it set up again.
 
I used to work the MPAN 11 area for a meter provider , the DNO was Western power distribution ( now part of national grid), they had Mocopa certified jointers that did work on all metering equipment. I would turn up sometimes on a job to do a meter shift and they already done the job for me. (happy days)
 