I had a commercial job few months ago, local electrician had installed some sockets in their comms room, that apparently had never worked.
Got to the job, strange place, lots of three phase mains intakes spread around the building. Anyway, found the problem, the dosey prats had supplied the sockets from a storage heater DB, labeled storage heaters off peak supply, quite obviously connected to a contactor and time clock.
Perhaps they were working out of hours, at a time when the board was live, and probably couldn't read, although if that was the case how did they pass the C&G 2382?
maybe if the board had been labelled in Polish?????