I think if you make any sort of enclosure (like mdf cupboard or something ) it is going to be outside zone eg. shower pump under a bath tub.
 
Had a similar issue before but with wrong length not CSA.

Ran around 100m of 16mm SWA out once, outside, through a building to then find out they had delivered around 30m short!...

Had to wind it all back on the drum. Nightmare!

Sent the bill to wholesaler though for our time!...
 
Out of interest, did he pay?

They sent it on to there cable suppliers who admitted the mistake but didn't know how it happened and they paid up for the Labour.

It was the actual cable suppliers who came and picked up the old drum and dropped the new one off within an hour or so.

IIRC I think it all may have been done in the form of credits.

I nearly dropped through the floor at first though as I thought I must of measured the cable up wrong!...until we measured the cable.
 
I’ll hold my hand up:
Guess who ordered a 185mm 3½ core 10 meters short. Our company never found out, I’ve never done a joint so fast! Fortunately we had a bit left over from another job.
Deception comes back to bite you in the bum. A short run from the main board to a sub board, quote the boss “there’s enough left over from that other job”.
Bloody piky’s will nick anything!

One that wasn’t my fault:
Cable supplier was supposed to delivered four drums of 120mm 11KV PILC. It stood in our compound for a while. I eventually got around to checking it, it's 70mm?
Several phone calls later I tracked our cable down, the cable supplier had mixed up our delivery with a similar due to be delivered the same day. It was at another company about a mile away. Thankfully they’d just stuck it in their compound.
 
apparently it was 4mm , 4 core so just wacked it in using just 3 of the cores, wholesaler was like if you bring it back we will replace.i was hoping for another 25 meters free!
 
i have to go back to job so may double up but it was getting dark last night and they wanted it done.
 
I feel for you , it happens to us all !
I am sure you will have done , but you best keep the clients informed as well . You mention that 6mm is what is on the quote , so if for any reason another spark comes along in the future and finds a paralleled 4mm ( if you go that way ) , he will be straight back to the client giving it large at what a bodge he has just found . ( It is only going to get worse with Electrical Trainee's )

I am sure you already know that reputations take a life time to build and maintain , and just one misunderstanding to ruin for ever !
 