Re: Th e1 day rewire

4 blokes 6.00 am start, surface trunking. possible.
 
Re: Th e1 day rewire

Of course there's 2 days snagging ;)
 
Re: Th e1 day rewire

Where are you referencing this from, ive watched 60minute makeover and they can squash a day + work into 60mins...... yeah right - nice when all the carpets pull up in one piece, the walls dont need poly-filler, the existing electrics are always ok and they never get carpet fluff on the wet skirting boards.
 
Re: Th e1 day rewire

Just from a post I saw earlier on the forum.

Have also heard it mentioned whilst out and about.
 
Re: Th e1 day rewire

I dont do rewires any more but over the course of 10 years we performed 1000's of domestic rewires from one bed flats to four bed house all within the day to a very high standard . its easy just needs organised staff .

The way we did it was like this

5 men

1 man = Wiring and Consumer unit.
1 man = upstairs First fix and second fix
1 man = Down stairs first and second fix excluding kitchen.
1 man = kitchen

5 man = this would depend on house type but he would help in one of the above excluding wiring.

Please bare in mind we where rewiring council propertys and every site had same house. so once first one was over it got easier and easier per house.
 
I used to work for a company who specialised in them, its very possible, 3-4 people, graft graft graft, also done them myself outside of the company

Some squads were getting done by 2.30 in some areas

Another contractor does the plastering up, snagging is also bare minimum because the prices are so rubbish now the squads cant afford to leave anything out
 
Re: Th e1 day rewire

Used to be my old gaffers bread & butter did this.

Empty council house rewires, basic spec, surface trunking, 3 men 1 day.
 
The ones ive known are all chased, chasing machine and chisel guns

Most are occupied council houses, the odd void property here and there
 
Re: Th e1 day rewire

Within the scope of design you effectively need to wire enough power points to for modern needs and avoid systems that will adversely effect the appeal and price of the property, i therefore can't see how this can be achieved in a 24hr rewire, trunking out a domestic job through-out would lower the re-sale value of the house and should be avoided but if the owner decides its the chosen method then he should be made aware of the consequences of a cheap rushed job. Id love to see the spec of one of these 24hr wonder rewires.
Seen it in council houses but its was done as a cheap alternative prior to the right to buy policies , so as to cut costs and give the tenants cheap but functional electric system so they didnt try get sale price reduction because it needed a rewire when the tenants bought it out.
 
Re: Th e1 day rewire

A company I worked for rewired 3 bed houses, occupied, in a day, 5 man team. Plasterer would go in a few days later then the tester a few days after that, then the decoraters.


Jay
 
Re: Th e1 day rewire

One day rewires are pretty standard and once you've done the first in street the rest are easier, all wired to spec and upto 17th, usually chased with machine except flats with concrete roofs/ floors
 
Re: Th e1 day rewire

Work done = man/woman hours spent. Of course if you chuck loads of people at a job you will get it done faster. The TV makeovers have 10 tradesmen plus 30 volunteers plus a team of researchers sourcing materials. NO wonder they get it done in 3 days.
 
Re: Th e1 day rewire

One man twenty years and I still never got it right. Divorce put an end to the project.
 
Re: Th e1 day rewire

Moved in this house 7yrs ago started rewire on the 16th still half done now on 17th and busmans holiday comes to mind .... i bet their are many similar tales Tony to ours.
 