Re: Th e1 day rewire

Within the scope of design you effectively need to wire enough power points to for modern needs and avoid systems that will adversely effect the appeal and price of the property, i therefore can't see how this can be achieved in a 24hr rewire, trunking out a domestic job through-out would lower the re-sale value of the house and should be avoided but if the owner decides its the chosen method then he should be made aware of the consequences of a cheap rushed job. Id love to see the spec of one of these 24hr wonder rewires.
Seen it in council houses but its was done as a cheap alternative prior to the right to buy policies , so as to cut costs and give the tenants cheap but functional electric system so they didnt try get sale price reduction because it needed a rewire when the tenants bought it out.

All rewires had more double sockets and lights then previous

lounge 4 -6
bedrooms 3-4
kitchen 3-4 all appliances one fused spur with low levels.


etc etc.


Trunking is only used in flats.
houses are usualy chased in or faster fixed boxes used on plaster board walls.

during 2009 - 2010

I had three teams wiring one house each per day for 12 mths.

and the standards where very high I have some images I will dig them out.
 
Re: Th e1 day rewire

Il stand corrected then, but i just going from experience of owners living in house rooms full of junk but suppose if you've got a sparkie in every room or 2 its more than feesable.
 
Re: Th e1 day rewire

Sometimes we moved all funiture , dust covered the whole house , rewired house , tidy up put funiture back for 4pm
 
Re: Th e1 day rewire

did one in august, was up against as the 96 year old fella that lived there WAS coming back friday at 12, I was up tuesday at 5, working at 6, till 10pm, and RUNNING all day pouring with sweat. It was a 3 bed detached with a few out buildings and a burger because walls were all engineering (!) brick, I started the tuesday, had one other helping me on the thursday and it was all done friday at 11:30am ....... and to a very high standard I might add :wink_smile:. OK ok I know thats not in one day but as someones pointed out, "doing stuff" takes time, theres not really any way round it, we're not magicians, if you put the man hours or hours and many men in, it'll get done. Unusual for me as I was used to insurance flood damaged places so other rewires tended to be over weeks/months as things ticked along
 
Re: Th e1 day rewire

Where are you referencing this from, ive watched 60minute makeover and they can squash a day + work into 60mins...... yeah right - nice when all the carpets pull up in one piece, the walls dont need poly-filler, the existing electrics are always ok and they never get carpet fluff on the wet skirting boards.
I love the way they plaster the walls and then paint them, all within that 60 minute window. Oh and they hang the pictures too.Dread to think what sort of state its in. I'd be stuck testing any electrical changes with the cameras looking elsewhere :juggle:

I wonder if them or DIY SOS and the likes test or bother with Part Pee and notification when required?
 
Re: Th e1 day rewire

A company I worked for rewired 3 bed houses, occupied, in a day, 5 man team. Plasterer would go in a few days later then the tester a few days after that, then the decoraters.


Jay
There's the problem. Occupied house. Tester weighs in several days after rewire is done. Who dead tested the circuits then? Or was it an all's well if the MCB and RCD hold scenario? I can't imagine the place was left de energised until then.
 
The rewires our company completed were tested on the day, everything was tip top on them as the councils clerk of works checks every property

Stop trying to beleve it cant be done because it can
 
The rewires our company completed were tested on the day, everything was tip top on them as the councils clerk of works checks every property

Stop trying to beleve it cant be done because it can

Yep sure can 3 bed maisonette done today by 4pm, team of 5. Holes cored for fans all tested by 4pm. No snagging or else we have to go back to do it which costs us time on next rewire.
 
I am in awe that all the work can be done and all the testing/paperwork done and filled out to a high standard in just 1 day. Hats off to you guys.
 
Re: Th e1 day rewire

There's the problem. Occupied house. Tester weighs in several days after rewire is done. Who dead tested the circuits then? Or was it an all's well if the MCB and RCD hold scenario? I can't imagine the place was left de energised until then.

The guys who did the rewire did some tests and filled in a test sheet. And the clark of works was happy with that. I went and did the full I & T after all other trades had been and gone i.e kitchen fitter,plumber, plasterer, decorater etc. I would always try and get in as soon as possible but I got told to do them in a certain order.

Jay
 