recently been to look at a job where the customer wanted LED downlights installed in there bathroom. Once up in the loft i realised the job wouldnt be as easy as id hoped for ( are they ever ). The first thing i noticed was very old rubber cable (live/neutral but no c.p.c). I wasnt initailly concerned as i thought this may not be in use, especially as additions/alterations had been carried out using T+E however i was soon to be found wrong. It turned out that the old cable was in fact the upstairs lighting feed. The house had recently been decorated with fancy light fittings and switches so the look on the homeowners face and her line of ' but its been fine for years' was no surprise when i tried to tell her the dangers that could exist, and that the only viable solution was to rewire the circuit. Now luckily there is a redundant T+E shower feed in the loft that has been made safe in the DB. I plan on using this as a new feed, then with a JB in the loft rewire using existing switch drops in new T+E. My problem/issue is at the mains, where i have a PME supply, water and gas bonds are fine. The DB itself is a split load Wylex board and there are no spare ways on the RCD protected side for me to use, i was thinking of using an RCBO to get me round this,but when in the board i noticed a circuit that is supplying socket outlets that was also on the unprotected side. I will obviously carry out an initial verification on my new circuit, and should my results be satisfactory is that as far as i need go? i was wondering would i be best to advise the customer on DB change or additional work to sort the sockets issue. Or as i havnt actually worked on that circuit do i not need take responsibility and just maybe make a note/recommendation on my test results?