    PIR Unsatisfactory, what do you write?

    Just thought i'd see what all you write on a PIR that is UNsatisfactory.. For the time until next inspection? And are you putting a Next inspection date label on the board even if the house is full of 1 & 2's? I've seen and heard a mix of things, also some people are re-doing a full PIR when...
  2. C

    Periodic Inspections

    I’m carrying out a periodic on thursday on a property that has an old installation. I’m testing it to 17th edition regs, so surely the entire installation will be deemed unsatisfactory - is this correct? ie. no RCD, no MCBs (fuses), under rated tails, under rated main bonds etc.... Where does...
  3. T

    PIR... 3036 what do you do?

    To the point... Someone asks you to come in and do a PIR on there 3 bed semi. You walk in and see straight away that they have an old 3036 Re wireable circuit board.. Do you instantly know at the end of this you will be giving an unsatisfactory and saying "You need a new dual RCD board...
  4. N

    1mm cpc in ring mains

    Hi guys my local authority have asked me to carry out some PIR's on some properties with regards to upgrading them to 17th edition. I suspect that the rings will be 2.5 t+e and will have a 1mm cpc, if left will the properties comply with a 1mm cpc using a 32 A mcb (obviously RCD protected) or...

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electric Underfloor Heating Electrician Courses Heating 2 Go Electrician Workwear Supplier
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

Advert

Daily, weekly or monthly email

Advert