Following on from a completed job I have been asked to do a install for a staff laundry 4 dryers 4 washers 2 lighting circuits up to me how a carry it out,but they propose bring in 2 phases from the main staff accomodation building so there will be a sub 3 phase board with only 2 live phases, whats the protocol for this I have never thought about this before, using a couple of phases from a 3 phase yes, but bringing in 2 phases for general distribution ???, when I queried it I was told the main reason is they laid the wrong cable 3 core instead of 4, I am not saying I know this is wrong just never heard or seen this done,comments anyone