S

Spaced

Good evening all, could anyone please advise as to whether there is a recommended period before a full rewire is considered? The property in question is a 3 storey town house that has been vacant for 14 months and has suffered from a degree of water ingress in both the cellar whet the cu is situated and also the loft. The wiring is pvc/pvc to a Wylex ceramic type board.

Regards
 
Hard question to answer, suggest a Periodic Inspection be carried out first which will give you all the info you require.
Although it sounds like a new c.u. is required.
 
Last edited by a moderator:
Good evening all, could anyone please advise as to whether there is a recommended period before a full rewire is considered? The property in question is a 3 storey town house that has been vacant for 14 months and has suffered from a degree of water ingress in both the cellar whet the cu is situated and also the loft. The wiring is pvc/pvc to a Wylex ceramic type board.

Regards

btw, without seeing the site, I would go out on a limb and say a installation that has rewirable fuses then it probably requires general modernisation and a rewire would be a good idea.

I would have thought the wiring would be ok, maybe the use of dehumidifiers in the cellar to dry out the installation.

Richard
 
I'd of thought an IR test would tell you if the cable is up to the job or not.. Periodic will tell you all you need to know.
 