Putting a tender together for a project if 35 new build houses , I have my own in house estimator but any pointers with regards to pricing it's for a large construction company
 
Suggest you put a qualification in to say that the supplies to each house is the responsibility of others and that you can only carry out inspection and testing on a suitable supply or something along those lines.
 
35 houses?

I would be looking at getting a solicitor to write up a contract of T&Cs in regards responsibility, payment etc. on a project that size.
 
Careful not to price it for continuous work.
IE out of one into the next.
Nowadays they tend to build when sold, you could be back and forward for years!

Boydy
 
Ask to see the construction programme if you haven't already got. If its going to take years you will need to consider rise in costs etc.
 
What kind of pricing structure would be used

price per house etc ? Hourly rates to be competitive
 