The trolls thread that has been deleted regarding "108 Ohms on the Ze" (or the Zs or R1+R2, he couldn't answer us on that one). Here is a break down on what you need to do:-
1. When doing your tests, are you coming inside the box (cu) or outside the box (cu)?
Inside the box crocking your cable end = Ze
Outside the box probing both ends to satisfy your ring = R1+R2.
Now if your coming in and out of the box at the same time or adding up the outcome of probing both of them, that's your Zs.
2. Make sure the recipient (customers) ring is entact. Nothing worst than pulling out (of the job) at the first red sign of trouble.
3. You need to put the end of your probe on the tip of the nipple (term screw) and do the same with the other nipple. You might need a friend to help you with that if your lead isn't long enough.
4. If your probing isn't adequate, you need to look at each backbox, don't be shy get your fingers in there. Yes it may be old, dirty and fragile and you may even find some carp but a man's got to do what a man's got to do to satisfy the customer.
5. Now that you know where your coming from and where you need to put your probe after fingering the backbox, you need to concentrate on penetration. Your end (of the wire) can't satisfy an end result if its only half way in. Make sure you pull off enough skin (cpc sleeving) off your end so you can penetrate the hole (term block) correctly.
6. Ensure the hole (term block) is ready for your penetration. You've got to screw it the right way, anticlockwise slowly but firmly until its almost at the top, just about to pop out. Stop at this point and put your end in (the cpc wire that is).
7. Now screw slowly but firmly again but this time clockwise. Not to hard, not to soft. You need to screw it just right but only experience will teach you this.
8. Hopefully by now your customers ring is good to go. Put your probe on each end (get a mate to help if you can't handle it by yourself) and push the button. If you've followed all my step by step instructions you and your customer should be happy with the result. If not get a proper man in to do the job.
BTW lads, if any of you have read too much into this post and believe its of a sexual nature, I've just been talking about electrics. You've just got a dirty mind LOL.
Tens mins and this will be in the Arms.
1. When doing your tests, are you coming inside the box (cu) or outside the box (cu)?
Inside the box crocking your cable end = Ze
Outside the box probing both ends to satisfy your ring = R1+R2.
Now if your coming in and out of the box at the same time or adding up the outcome of probing both of them, that's your Zs.
2. Make sure the recipient (customers) ring is entact. Nothing worst than pulling out (of the job) at the first red sign of trouble.
3. You need to put the end of your probe on the tip of the nipple (term screw) and do the same with the other nipple. You might need a friend to help you with that if your lead isn't long enough.
4. If your probing isn't adequate, you need to look at each backbox, don't be shy get your fingers in there. Yes it may be old, dirty and fragile and you may even find some carp but a man's got to do what a man's got to do to satisfy the customer.
5. Now that you know where your coming from and where you need to put your probe after fingering the backbox, you need to concentrate on penetration. Your end (of the wire) can't satisfy an end result if its only half way in. Make sure you pull off enough skin (cpc sleeving) off your end so you can penetrate the hole (term block) correctly.
6. Ensure the hole (term block) is ready for your penetration. You've got to screw it the right way, anticlockwise slowly but firmly until its almost at the top, just about to pop out. Stop at this point and put your end in (the cpc wire that is).
7. Now screw slowly but firmly again but this time clockwise. Not to hard, not to soft. You need to screw it just right but only experience will teach you this.
8. Hopefully by now your customers ring is good to go. Put your probe on each end (get a mate to help if you can't handle it by yourself) and push the button. If you've followed all my step by step instructions you and your customer should be happy with the result. If not get a proper man in to do the job.