hi all,
i have been asked to install bulkhead lights to a building site hoarding, about 200 metres worth.

havent visited site yet but am told they will be on 240 supply and run in swa.

all the sites ive seen before have been 110v and run in arctic cable so question is, do 240v lights comply on site??
 
Reduced LV is recommended for portable and local work lights,but no restrictions on other lighting....other than TNCS not being used,and types of cables which may be installed,.....all in section 704.
 
Must admit, I've only done this in 110v with standard bulkheads and a 110 lamp running off a transformer. This was in the public street though so don't know if would be different if on private land etc. I was following recommendations from local H&S officer who attended site and wanted red lights facing the road and white for the path. I think you have to weigh up chances of damage, the higher the chance the more likely kids will be hanging from them or trucks hitting etc.
 

OFFICIAL SPONSORS

OFFICIAL SPONSORS

Thread statistics

Created
flukey,
Last reply from
needasparks,
Replies
2
Views
5,441
Back
Top