Just looked at a job to replace an old re-wire able four way box. Quick test revealed good Ze and IR spot on. Only one problem, the b&q 10 way customer bought box will amazingly not fit into the small cupboard alongside the main intake, meter, and existing fusebox.
The meter tails can be moved, but I would have to extend the cables to accommodate the new fusebox.
My question is, would it be o k to crimp the cables to extend them, if so how would you go about covering all the connections to tidy them up?
Thanks in advance!
The meter tails can be moved, but I would have to extend the cables to accommodate the new fusebox.
My question is, would it be o k to crimp the cables to extend them, if so how would you go about covering all the connections to tidy them up?
Thanks in advance!