And what about the monkey that did it and the lack of certification.
Well when I asked for the cert I was told I didn't need one, and then when I pressed him for one he admitted he wasn't able to give me a cert and that someone he works with would come and verify his work and provide one "if I wanted" (like I hadn't already just insisted on one...). I highly doubt that will happen somehow, so I have no idea what my options are now. I'm not happy to leave it without any sort of cert.
 
I would be going to the builder as the work is not complete without certification including Part P notification. Tell the builder you are seeking legal advise.
 
Hello all, I’m back with an update… the ‘electrician’ builder got his actual electrician in to do what was necessary (all the changes members here said about) and I now have an NICEIC headed EIC. However they continue to tell me I do not need part p/notification because the building itself is under permitted development. I have pushed that I want this notification done to be told it’ll mean local authority/building control visiting and all the development being under building regs.

I’m sure this is not true and the point of the electrician notifying is to save the building control needing to come round. Am I right?
 
Last edited:
Hello all, I’m back with an update… the ‘electrician’ builder got his actual electrician in to do what was necessary (all the changes members here said about) and I now have an NICEIC headed EIC. However they continue to tell me I do not need part p/notification because the building itself is under permitted development. I have pushed that I want this notification done to be told it’ll mean local authority/building control visiting and all the development being under building regs.

I’m sure this is not true and the point of the electrician notifying is to save the building control needing to come round. Am I right?
That is utter crap

The building may well be under permitted development but the Electrical work was notifiable.

Building Control will not need to be involved unless the Electrician is not part of a scheme and therefore not able to notify their own work. That will require a fee and them requiring certain documents and depending on how it plays out they might insist on an EICR.

This is something the NICEIC Electrician should have done but may be reluctant to if it isn't their work. Have to ask what the relationship is between the two Electricians and the Builder.

So at the outset the original Electrician wasn't going to give you an EIC (Electrical Installation Certificate) or notify Building Control.

Then an NICEIC Electrician has given you an EIC but failed to notify Building Control.

You still need the Building Control Notice doing.

Is this a reputable firm? They sure don't seem to be.

The threat of it not being under Permitted development, does it comply with permitted development? You could be in a sticky situation if it doesn't.

As I said Building Control will not be involved if they can self certify if they can't and the route is through building control and the development doesn't comply then it could get messy. Doubt Building Control would visit most likely will want the fee and documents and if not satisfied would want an independent EICR doing.

That said different BCs handle this differently and what they require,
 
If the name or logo appears on any paperwork, van etc, showing the name of any scheme provider like NICEIC then it is down to the electrician to notify LABC, otherwise it is down to the homeowner, and I have also thought this is a silly rule, as most people are not looking for NICEIC logos, they assume an electrician doing domestic work is a scheme member.

I was one of those caught out, where the builder had not completed the application, but I had not realised he had not done it, so when the builder ran off, and I took over the job, I told the LABC that I was taking it over.

Had I kept my mouth shut, likely I would have been OK, but one can't untell them, so I got permission to continue, and when I looked at trying to get some money back, the LABC has beat me to it, and the company had been wound up.

Anyone can complete an EIC, it does not require one to be a member of any club, if they have the skill to install the electrics that means they have the skill to complete the EIC, so putting it in simple terms, if he can't fill in an EIC he/she is not an electrician.
 