Hello, I have tried to search the forum but have not found anything although this must have been asked a thousand times.
When completing a board change for example and there is no end to end on the neutral does downgrading the mcb to a 20amp and effectively running two radials from the same MCB comply with BS7671 ?
End to end on r1 and r2 are good (I just can not for the life of me find the break in rn, other than to identify its likely under the floor under some nice new tiles)
Im happy to do some reading if someone could point me to the correct chapter in the book.
And if this is ok (2 radials from one MCB) having taken into account demand, how would the results be recorded on the schedule ?
When completing a board change for example and there is no end to end on the neutral does downgrading the mcb to a 20amp and effectively running two radials from the same MCB comply with BS7671 ?
End to end on r1 and r2 are good (I just can not for the life of me find the break in rn, other than to identify its likely under the floor under some nice new tiles)
Im happy to do some reading if someone could point me to the correct chapter in the book.
And if this is ok (2 radials from one MCB) having taken into account demand, how would the results be recorded on the schedule ?