A

Anonomoose

Went to price a job yesterday. labour only, rewire 3 flats + communal stairs, 2 x 2 bed, 1 x 1 bed. All walls stud so no chasing i origionally quoted £5000 he said far too much. I based it on £1800 each for 2 beds and £1200 for 1 bed then £200 for communal stairs anyone think this is too much. Im based in the south east near the coast for pricing reference.
 
What do you recon, 3 weeks work?

As a rewire on stud possibly less as should be easy to pull cables and back boxes in place, a bit difficult to work out blind.
 
Last edited by a moderator:
I only have the drawings as pdf so cant post it so the main gumph below.
Labour only

3 flats
2 x 2 bed
1 x 1 bed
1 x staircase

external walls going to be boarded
internal walls stud.

each flat 25 downlighters
20 D/s
5 smokes for some reason think the architect is paranoid
2 x TV in each flat
2 x sky in each flat
5 x sw fu spr

all ceilings down all walls down or gutted

Really appreciate help on this as its annoying me him saying his budget is £2200 think thats a bit low
 
I think £2200 is too low also, that said what other work have you got on.

Worked out at per point your original quote seems cheap!

I think its 3 weeks work with all testing, a bit of bread and butter work, so go in at £3k and take no less? Or as Flukey says walk!

Depends on you and your order book!!!

Having had a really quiet Jan, In hindsight I would have taken a job like that at £2.5k, but not now as things are really perking up!

Your call, be interested to know how you get on
 
Last edited by a moderator:
I would have thought 3 weeks work so about 3k esp if not much work on.

I went in cheap on a job the other day but agreed that I would only work on it 3 days a week so could fit it around other work. Client was happy and am almost finished it now. Can work out well to keep you busy if he will let the elapsed time extend (even if the effort days are still 15).
 
why is a total rewire required, is it that old for a building with stud walls.

is a periodic inspection not adequate to asses the install first?? maybe this would be an alternative approach to the client with a low budget
 