what would you charge for chopping in 15 double sockets for a flush finish which are currently surface mount, plaster/brick wall. any advice greatly appreiciated.
 
plastering as well? do it on an hourly rate if your unsure, I'd think its a days work so 150 to 200
 
plastering as well? do it on an hourly rate if your unsure, I'd think its a days work so 150 to 200

Yes that sounds ok
You could do what I try with these sort of jobs and get a chisel monkey with limited brain capacaty and little money and get him to do al the hard work for you
 
cheers lads, sound advice, just me on my own pretty crappy job but welcome none-the-less!
 
Sounds like a ****ty job to do, could take longer than expected. Maybe it'll be rock solid engineering bricks!! Then again the bricks could crumble away and leave you with nothing to fix to.

What about the cabling? If I were you I'd estimate how long it'll take and then double it, and add a bit on top!!
 
Last edited by a moderator:
Sounds like a ****ty job to do, could take longer than expected. Maybe it'll be rock solid engineering bricks!! Then again the bricks could crumble away and leave you with nothing to fix to.

What about the cabling? If I were you I'd estimate how long it'll take and then double it, and add a bit on top!!

Just a note, in my experience where the sockets are surface mounted I usually find that the bricks are rock hard engineering as the above guy has stated so you have to account for this!
 
If you're planning on doing a lot chasing in i would save yourself time and buy a double bladed 4.5 inch grinder with sprung cover( Makita SG1250) and extraction unit plus a good quality breaker from the off. You will get the money back after a few jobs and save yourself a lot of knuckle bashing and time. I find the diamond tipped blades manage all but the hardest of hard walls. As regards to time you should be able to remove the old wiring, chase and tube the new sockets in, in a day. Id get someone else to make the chases good !
 
this would depend on if customer wants brick dust all over the house or kept to a minimum, recently done similar job 12 boxes all made good took day and half as bricks were rock hard and done by hammer and chisel charged £200 they were pleased i somehow felt i should of charged more for my troubles.
 