Discuss Who should pay for my time? in the Business Related area at ElectriciansForums.net

Reaction score
0
I was recently called back to a new house I had just completed by the customer regarding an intermittent fault.

It took a while to diagnose that a small water leak from the boiler flow pipe was gathering in the Honeywell valve and knocking out the RCBO when calling for Hot Water.

Having invoiced the client for the hours worked they have passed my invoice onto the plumber whose leak caused the fault. He is refusing to pay.

Am I right in thinking that if the client requested my services then they are liable to pay.

I’m guessing the plumber should reimburse them.

Can anyone clarify this?

Thanks in advance

John P
 
As said above, if you order a service and it is delivered, you should pay for it.

What you installed originally is not faulty due to workmanship or manufacturing fault.
Therefore it is a chargeable call out.

Would they also expect you to bill the post office if they reversed the van into a garden light?

Simple. They asked you to diagnose fault and repair.
You found fault was non electrical and showed the the root cause.
Definatley they are liable to pay the bill.

P.s. Just noticed you are a new member.
Welcome to the forum, hope you have some fun here.
 
just to add with this post ,if a customer ring me up then we say over the phone when I start working on the job regarding faults that I want paying when it is finished . if they agree over the phone then I will go out .if the plumber caused the fault thats third party .
 
Last edited:
You don’t go to Tesco, fill your trolley with frozen goods and ask them to bill curry’s because your 1 week old freezer from them broke down.
 
Welcome to the forum

I deal with ----s like this by:
Sending invoice
Sending 7 day notice (with expiry date stating when I will commence court action), along with a simple letter which goes along the lines of I expect payment for the service carried out otherwise the next action is court and there will be additional costs.

Filling out Simple Procedure form (Scottish Court) and sending it to them

Last guy I had (this year for £43) paid at 10.50pm on the day of expiry of the 7 day notice.
 

Reply to Who should pay for my time? in the Business Related area at ElectriciansForums.net

Similar Threads

Hi Absolutely 0 knowledge of this so excuse language / terms / explanation. Electric only ground floor 2 bed flat ( 3 external walls) On peak...
Replies
59
Views
5K
One of the oddest jobs I've ever had today. Called by a plumber I know who had attended after a leak through the kitchen ceiling from bathroom...
Replies
24
Views
6K
Hi. I have been having a problem with my AEG 7000 Series Washer Dryer (L7WEG851R) tripping my main fuse box over the last week. I am trying to...
Replies
15
Views
9K
Im seeking advice from a job we have done with the most difficult customer of my whole career. We're a family business of 50+ years and take pride...
Replies
81
Views
11K
Last time I posted on forum it was on the thorny issue of over unity machines which alas got confused with perpetual motion -- and other supposed...
Replies
72
Views
8K

OFFICIAL SPONSORS

Electrical Goods - Electrical Tools - Brand Names Electrician Courses Green Electrical Goods PCB Way Electrical Goods - Electrical Tools - Brand Names Pushfit Wire Connectors Electric Underfloor Heating Electrician Courses
These Official Forum Sponsors May Provide Discounts to Regular Forum Members - If you would like to sponsor us then CLICK HERE and post a thread with who you are, and we'll send you some stats etc

YOUR Unread Posts

This website was designed, optimised and is hosted by Untold Media. Operating under the name Untold Media since 2001.
Back
Top
AdBlock Detected

We get it, advertisements are annoying!

Sure, ad-blocking software does a great job at blocking ads, but it also blocks useful features of our website. For the best site experience please disable your AdBlocker.

I've Disabled AdBlock