I went to a job this afternoon to replace a couple of bathroom lights. Did a Zs before starting and got 66.3 Ohms. So I investigated further and found the Ze was 66 Ohms on a TNS system.
I phoned the DNO (UK Power Networks in Hertfordshire) to inform them of this. Firstly they asked me where I had done the Ze to which I said at the CU. They told me they wanted one done at the head. So they gave me permission to cut the seals to do a Ze at the head- this amazed me as I thought (officially anyway) they didnt allow us to cut seals and play with their toys. This permission was given on the phone- should I have refused or gone ahead?
Secondly they said it wasnt an emergency, and they would prioritise those without power first and couldnt guarantee to come out within four hours. Now when I have had this situation before (Ze too high) the DNO have always said it needs to be fixed within fours hours so I told the DNO this and also pointed out that there were no RCD's present. They said they would try. I havent heard from the customer so I dont know if they made it within the four hours, I will phone the customer tomorrow.
I am what you like to call a 5 week wonder, I have the 2391 and have been doing electrical work for about 2.5 years.
Are the DNO correct in not giving it a response time of four hours or should they have been out withing four hours
I phoned the DNO (UK Power Networks in Hertfordshire) to inform them of this. Firstly they asked me where I had done the Ze to which I said at the CU. They told me they wanted one done at the head. So they gave me permission to cut the seals to do a Ze at the head- this amazed me as I thought (officially anyway) they didnt allow us to cut seals and play with their toys. This permission was given on the phone- should I have refused or gone ahead?
Secondly they said it wasnt an emergency, and they would prioritise those without power first and couldnt guarantee to come out within four hours. Now when I have had this situation before (Ze too high) the DNO have always said it needs to be fixed within fours hours so I told the DNO this and also pointed out that there were no RCD's present. They said they would try. I havent heard from the customer so I dont know if they made it within the four hours, I will phone the customer tomorrow.
I am what you like to call a 5 week wonder, I have the 2391 and have been doing electrical work for about 2.5 years.
Are the DNO correct in not giving it a response time of four hours or should they have been out withing four hours