In a perfect world you could easily get your hands on the most recent EICR and then copy all of the info over such as Ze and the tick boxes to your EIC. Then you'd only have to perform the same tests as you would with a minor works

Not sure I agree with that ..............I may consider this route IF I had done the EICR ......... but use somebody else's figures ........... no
 
I do plenty of small installs in a factory where I did an EICR in 2016. Plenty dis boards so I just do a zs at board in question and cert to suit.
Similar to WP, today used an swa, which used to feed a portacabin, for a small compressor in a new quick build...so it ticked the right boxes.
Trouble is, I don't want to start ticking another load of boxes, either....pain in the butt. :(
 
In a perfect world you could easily get your hands on the most recent EICR and then copy all of the info over such as Ze and the tick boxes to your EIC. Then you'd only have to perform the same tests as you would with a minor works
Thats assuming the eicr is worth the paper it is printed on and has not been done by a drive by cowboy in his bodge job van.
all well until you copy the results from such an eicr and they are made up when really the place is a death trap...
 
Another problem I find is with ind/com kitchen work, maybe in schools or shopping centres. They may be small jobs, such as gas cut out panel supplies. It's virtually impossible to get any supply info or access. In such cases it has to be a case of noting on the cert.
Imagine trying to get info or access at Manchester airport or Liverpool Echo arena. It's impossible....and, sometimes, your dealing with awkward sods who don't want to know.
 
If it's not practical to carry out a Ze test I would rather put the Ze from the current EICR and leave a note on the EIC than leave the box blank.

I asked this question to my NICEIC assessor and he said that it is acceptable as long as the EICR certificate number is stated in the notes on the EIC.

Obviously not ideal but better than LIM
 
I would agree that an EIC would be technically correct (just).
However if you considered the job as a long period job, you came in removed the old cable and replaced it with a new cable and also removed the old accessories on the end of circuit and put new ones in, still the same old circuit just with a new cable and accessories!
If the job had been done in stages each one would have been a minor works.
 
... you came in removed the old cable and replaced it with a new cable and also removed the old accessories on the end of circuit and put new ones in, still the same old circuit just with a new cable and accessories! If the job had been done in stages each one would have been a minor works.
For some reason reminded me of this classic :)
 
For this situation there should a cert for when you are just installing one or two circuits as others as said its not always posible to access the main incoming supply of large installations , You can not put LIM on a eir so what do you do ?fill the report with N/As .
 
For this situation there should a cert for when you are just installing one or two circuits as others as said its not always posible to access the main incoming supply of large installations , You can not put LIM on a eir so what do you do ?fill the report with N/As .
Depends if that means 'Non Applicable' or 'No Access'. ;)
 