Sounds fineSub board off the existing board for me, not a henley block. Then move a few circuits over to the new board to make way for the submain breaker.
Sounds fineSub board off the existing board for me, not a henley block. Then move a few circuits over to the new board to make way for the submain breaker.
Sub board off the existing board for me, not a henley block. Then move a few circuits over to the new board to make way for the submain breaker.
what is that a snakes and ladders ,one circuit only for that .see if any two lighting circuits can be put into one breaker

The OP only needs to install one circuit, if he can gain enough space for an MCB to feed a sub-board he wont need a sub-board!Sub board off the existing board for me, not a henley block. Then move a few circuits over to the new board to make way for the submain breaker.
new 3p circuit to be added
it depends what is the load .The OP only needs to install one circuit, if he can gain enough space for an MCB to feed a sub-board he wont need a sub-board!
Ah sorry about my post regarding a 13 Amp socket reread your post and it's a new 3 phase circuit that is required sorry if I confused the issue, my bad.what's your take on adding circuits to a full DB.
Warehouse unit,3p DB,full to capacity,new 3p circuit to be added,client refuses to upgrade DB.
Would you reconfigure a couple of circuits to allow for this new circuit.
No sh#t Sherlock.it depends what is the load .
Agree,& that may be the logical way to go,I doubt very much the client is gonna be happy with the idea of a new Db & costs.The OP only needs to install one circuit, if he can gain enough space for an MCB to feed a sub-board he wont need a sub-board!
I think it's rather silly to dismiss the idea of grouping together one or two circuits to gain enough ways, without knowing the loads/circuits involved it may be a perfectly viable option. There seems to be a trend on this forum of late to dismiss common sense solutions to a simple problem as a bodge, and advocate 'walking away' if the client wont pay for the perfect end product. Perfect is not always required as long as a solution is safe, compliant and keeps the customer satisfied.
well said tooth puller ,I could not say better me self.The OP only needs to install one circuit, if he can gain enough space for an MCB to feed a sub-board he wont need a sub-board!
I think it's rather silly to dismiss the idea of grouping together one or two circuits to gain enough ways, without knowing the loads/circuits involved it may be a perfectly viable option. There seems to be a trend on this forum of late to dismiss common sense solutions to a simple problem as a bodge, and advocate 'walking away' if the client wont pay for the perfect end product. Perfect is not always required as long as a solution is safe, compliant and keeps the customer satisfied.

tell your customer he needs to pull a golden egg out of duck A77![]()



Not always, a very blinkered and unprofessional approach to only see one solution to a very simple problem.Client refuses............SEE YA