By way of background I am a degree qualified electrical engineer (long ago and now retired) and this is a spur to provide power to the central heating controls. I have had a nightmare with the company I have contracted with to replace the existing boiler. I am trying to cover all bases to ensure that third time around there is nothing to go wrong.

As a consequence of the boiler change, controls, zone valves and pump will be installed in the airing cupboard next to the hot water tank.

There is an immersion heater switch in the airing cupboard and I would tee of the back of that to provide the fused spur for the central heating. Is there any reason why this should not be done?

At the moment I do not know if the switch is on a spur or on the ring main for the sockets. Given the age of the property it will be black & red and maybe multicore instead of the standard 2.5mm single core cable today. This is a rental property and I am the landlord (my pension) so I do not have easy access.

If teeing off the immersion heater switch is acceptable – I can’t think of a reason why not. Then the next question is how.

The existing switch is flush mounted and I don’t want to go digging a channel in the wall for the spur. My tenants have suffered enough disruption. My thoughts are, either:
  • Take a 25mm (or deeper) surface mount pattress, drill out the brass screw inserts and through. Refit switch to pattress with longer screws into the existing back box. Tee off the back of the switch.
  • Remove switch replace with 30A JB and tee off the JB for the switch and fused spur.
The work will be done by an electrician (assuming they turn up), but as I said above, I am trying to think of everything that could go wrong and plan for it.
 