J

Jack of all

I am doing a complete rewire, I'm not part P scheme registered, so having building control inspect for me.
I'm about to call them in to check my first fix, so I've chock blocked everything out for the insulation test & R1+R2 tests. I'll test it all myself & they can have the results & check them themselves if they wish.

My question is should I have used earth sheathing, it seems a waste as it's all temporary connections.
 
Surely they will want to do a visual inspection after 1st fix and test the installation after it's been 2nd fixed?
 
I've seen chock blocks all wrapped up in insulation tape, I'm guessing they're live...
I just thought that seeing bare copper, the inspector might not like it ?
 
The building control people will not usually have the skill to do any test or inspection of an electrical installation. I would expect the work to be done by a contracting electrician on their behalf.
With this in mind the likelihood is he will do a visual inspection only

There is nothing wrong with your action of testing prior to plastering and boarding,however,it would not be something the inspector will expect to be doing at first fix stage and will no doubt use only his eyeball tester for this exercise

The probability is he will be looking at routing of cables in safe zones,using grommets for cable entry to boxes,where the holes are drilled and so on

Earth sheathing? I refer to that has earth sleeving

If you have bared back the copper cores you may find they get oxidised
I hope they are to be re made at 2nd fix

Over cautious can be counter productive as in above reason, testing at first fix is not usual in house wiring although in other circumstances it is a good decision
 
I'm not a House basher...... This is my own house, so I have no experience with house rewires. I'm up to speed with the technical specs but have not done domestic site work.
You won't find me asking help on a star Delta soft start panel...

Thanks again for your feedback..
 
I'm not a House basher...... This is my own house, so I have no experience with house rewires. I'm up to speed with the technical specs but have not done domestic site work.
You won't find me asking help on a star Delta soft start panel...

Thanks again for your feedback..

Sounds like ' housebashing ' is a bit to easy for you. Maybe get one of us ordinary electrians to do the job and you stick to your star delta soft start panels.......
 
If you're just doing IR and continuity, then leaving off the Earth sleeving is fine.
As to whether the inspector will have a problem with it, that's anyone's guess.
 