B

beanzntoast

Hi,a simple scenario for most of you.hope this makes sense if you was doing a consumer unit change to upgrade it to 17th edition in a 3 bedroom terrace house (not more than 100m sq)& you found the whole house on 1 ring circuit on a 32 amp re-wireable fuse would it be part of the job to seperate the circuits so the upstairs & downstairs are seperate & the kitchen had it own circuit & if not part of the job & they didnt want them changing (cost),could you put them all on the same mcb (covered by an rcd)& just advise of the situation on the test certificate.would this be the best way forward,
thanks jason
 
all you have to do to comply is do the best you can with what is there
you dont have to worry about splitting the exsisting
 