From the video I 'think' power is injected to the overhead lines at regular intervals; perhaps this power is transformed down from a higher voltage. For me the quoted voltage is too low to be efficient. I guess the trial, as stated in the video, had the address the fire brigade's and police's concerns about a higher voltage over a busy motorway.I have to admit that did go through my mind when watching the video.
IIRC they talked about "tram voltages", and I assume that means something in the order of 500V DC. If they split the rails +/-250V then that's gone a long way to reducing the risks.
But unlike trams, they aren't connected by metal wheels to an earthed metal rail - so I could see there being a risk if the insulation fails. I guess these would have to be Class II double insulated since there's no means t provide a reliable earth.
Also, there were some clear images of the tops of the collector pick-ups - complete with significant wear grooves in them. On railways, the overhead lines weave side-side so that the pick-ups wear across a significant part of the width and the wire never rubs in one place for any length of time. Otherwise, it wears grooves in the pick-up contacts (IIRC graphite blocks help in place by vacuum on trains) and then causes problems allowing the wire to move side-side easily.
I wonder if the driver had been following the wires - because I did notice them weaving in the same way as for railways which should have avoided the grooves.
Also intersting to consider the currents involved. If we assume (for simple mental arithmetic) 500V DC, then that's 2A/kW, or 1.5A/hp. Given that trucks are generally in the "hundred of hp" range - 500hp+ not being uncommon - then there's significant currents involved. I know it's going to be lower when cruising along the motorway, but they'll also be re-charging to cater for when they've been off the network. So probably need to allow "a couple of hundred amps" per truck minimum, and we've seen how close some trucks can follow each other !
One can imagine trucks forming up as a line and 'cleverly' sharing their onboard battery and motor power so as not to overload a section of overhead line or when going up hill.
As an aside but has some relevance I understand the electric robot cranes at the Thames Gateway port near me co-ordinate their lifts and drops - this could happen on the motorway between trucks.